First article inspection (FAI)

First article inspection (FAI) is a detailed check of the first part made in a new production run to confirm it matches the drawing and specification.

An FAI compares a part made with the intended production tools, materials and process against every requirement on the drawing: dimensions, tolerances, materials, finishes and markings. The results are recorded in an inspection report. It is usually repeated when the design, tooling, process or production site changes, because any of these can affect the part.

Some industries use formal frameworks for this step. In aerospace, AS9102 describes how first article inspection is documented, and in automotive the PPAP (Production Part Approval Process) covers a similar approval of production parts. Outside these sectors, buyer and supplier usually agree in the contract which characteristics are checked and how the report is shared.

Example: Before approving serial production of a machined bracket, a buyer asks the supplier for a first article inspection report listing the measured value of every dimension on the drawing.

Related terms

Discover companies by sector and country.

Browse companies →

Frequently asked questions

What is the difference between a sample and a first article?
A sample may be made by hand or with prototype tooling to show the concept. A first article is made with the actual production tools and process, so it shows what serial production will deliver.
When should FAI be repeated?
It is commonly repeated after a change in design, tooling, material, process or production location, or after a long break in production. The exact triggers are best agreed in the contract.
Who performs the first article inspection?
Usually the supplier performs it and sends the report, and the buyer reviews or witnesses it. Some buyers also use their own staff or a third-party inspector.
What is First article inspection (FAI)? · Digibition